Moray Firth Energy · ask for it yourself

Ask for it yourself

Paid for by the public: as electricity billpayers, and as taxpayers standing behind the loans.

Many of the missing figures are held by the regulator, the system operatorThe National Energy System Operator, the body that keeps Great Britain's electricity grid balanced minute by minute. more › and SSEN Transmission. The law lets anyone ask for them, and they must answer or say why not. This page gives the addresses, the questions and the steps. Write in your own words, and ask only for what you want to know.

Who to ask, and under which law

Check each body's website for its current information-requests address before you send. SSEN Transmission is a privately owned company, not a public authority listed in Schedule 1The list in the Freedom of Information Act that defines which bodies the public can make FOI requests to. more › of the Freedom of Information Act 2000Legal rights to request information from public bodies (FOI) or environmental information from a wider range of bodies (EIR). more ›, so that Act does not cover it. Ask it for environmental information under the Environmental Information (Scotland) Regulations 2004, which is how SSEN Transmission handles these requests.

How to write it

The Information CommissionerThe regulators for information rights complaints: the UK Information Commissioner (ICO) for Ofgem and NESO; the Scottish Information Commissioner for SSEN Transmission, which handles requests under the Scottish regulations. more ›'s Office (ICO) says a request should have:

It also helps to number each item, to ask for copies by email in the form the body holds them, and to ask for a list of anything withheld and the reason for each. If the body has already published an answer, it may point you to it.

A letter you can adapt

Subject: Freedom of Information request: Shetland HVDCHigh Voltage Direct Current: the technology used for long subsea electricity cables, including the Shetland link. more › Link 2
(for SSEN Transmission: Environmental Information (Scotland) Regulations 2004 request)

Dear Sir or Madam,

Under the Freedom of Information Act 2000 (SSEN Transmission: the Environmental Information (Scotland) Regulations 2004), I would like to request the following recorded information about the project SSEN Transmission calls Shetland HVDC Link 2, which OfgemThe UK government regulator for gas and electricity, which sets how much network companies can charge billpayers. more › calls Shetland to Coachford (SHL256Ofgem's project code for this link: 'New 1.8GW HVDC link Shetland - Coachford'. more ›) and NESOThe National Energy System Operator, the body that keeps Great Britain's electricity grid balanced minute by minute. more › calls Shetland to Blackhillock. Please send it by email, in the form you hold it.

[the numbered questions below]

Where any of this is environmental information, please treat the request as also made under the Environmental Information Regulations 2004 (for SSEN Transmission, the Scottish regulations of the same year). If anything is withheld, please list each document or part withheld and the reason. If any item would exceed the cost limit, please tell me before refusing, and treat the other items as a request in their own right.

The cost of this project is recovered from electricity billpayersAnyone who pays an electricity bill. Most of the costs on this site are recovered this way, not from taxes. more ›. There is a strong public interest in seeing the costs and the reasons for the decisions.

Yours faithfully,
[your name]
[an address for the reply]

Questions you can copy

To Ofgem

  1. SSEN Transmission's submissions to OfgemThe UK government regulator for gas and electricity, which sets how much network companies can charge billpayers. more › for Shetland to Coachford (SHL256Ofgem's project code for this link: 'New 1.8GW HVDC link Shetland - Coachford'. more ›) in the transitional Centralised Strategic Network Plan 2 (tCSNP2Ofgem's transitional Centralised Strategic Network Plan 2 process, under which this project was assessed and put in the delivery track. more ›), including any capital cost estimateLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more ›, cost breakdown and needs case.
  2. Ofgem's assessment papers and decision paper on putting SHL256 in the delivery track (1 January to 31 December 2024), including any paper on the system operatorThe National Energy System Operator, the body that keeps Great Britain's electricity grid balanced minute by minute. more ›'s advice that it stay in the development track (tCSNP2 decision, OFG1164, 11 December 2024, paragraphs 3.89 to 3.95).
  3. The Pre-Construction Funding awarded for SHL256, as a project-level breakdown of the provisional £68.430 million (2018 prices) shown for SSEN Transmission's four-project portfolio.
  4. Any reporting received on the 31 December 2027 deadline to submit all material planning consents.
  5. Use, availability or power-flow reporting for the existing Shetland link (Link 1) since it started, and whether the 600MW capacity test in Ofgem's 30 November 2021 decision (paragraph 3.41) has been completed.
  6. Correspondence with SSEN Transmission about community benefitMoney a developer or network owner pays to communities near new infrastructure, recovered in full from billpayers. more › funding for SHL256 since 1 January 2024.
  7. Any cost-benefit analysis or bill-impact assessment for SHL256.

To NESO

  1. The cost-benefit inputs for Shetland to Blackhillock in the Beyond 2030 workbook and tCSNP2, including the generation capacity assumed and the capital cost assumption for the link.
  2. Both maturity assessments for the project and the evidence for each: the one that placed it at level 2, "Strategic Optioneering", in the March 2024 Beyond 2030 workbook, and the one that records level 3, "Design/development and consenting", in NESO's June 2026 Beyond 2030 update.
  3. Boundary flow and constraint data for the existing Shetland link since it started, and constraint paymentsMoney paid to a generator to switch off, or reduce output, because the grid cannot carry all the power it is producing. more › to Shetland generators by year.
  4. NESO's advice to Ofgem on putting the project in the delivery track (tCSNP2 decision, paragraphs 3.89 to 3.95).

To SSEN Transmission

  1. The site scoring and weighting used to drop Sandend and keep Boyne Bay and Boyndie Bay as landfallThe point on the coast where a subsea cable comes ashore and connects to the onshore cable route. more › options.
  2. Constraint mapping (GIS files) and grid references for both landfall sites and for the Cruchie and RivestoneThe two sites shortlisted for the Strathbogie Hub, north-east of Huntly. more › hub sites.
  3. The assumed easementA right to use a strip of someone else's land for the cable, without owning it outright. more › and working widths, trench depth, joint bayAn underground chamber where lengths of cable are jointed together; its size and number are not published for this project. more › and drilling compound sizes, construction time and vehicle movements for the 30km onshore cable.
  4. Environmental survey and scoping reports for the Aberdeenshire landfall and onshore route.
  5. Marine survey reports under European protected species licence EPS-00011333 and basking shark licence BS-00011332.
  6. Any noise assessment for the proposed Strathbogie HubThe proposed converter and substation site north-east of Huntly where the onshore cable from the landfall would terminate. more › converter stationA large facility that converts electricity between the direct current used by a subsea cable and the alternating current used by the onshore grid. more ›.
  7. The calculation behind any community benefit figure for the Aberdeenshire part of the project.

What happens next

Source: ICO, guidance for the public on official information: preparing and submitting a request; what to expect; what to do if you are dissatisfied (read 7 October 2026).

Keep a record

Your request goes, in your name, only to the body you write to. Nothing reaches this site unless you send it. If you receive a document that fills a gap on the missing figures, the address is on About. Figures are published with the document they come from, never with the sender's name.