The words are the author's; in the film an AI voice reads them. This film's figures come from the documents named on screen, listed in its own fact base rather than the evidence registerA table listing every figure used on these pages, with its source document, its class and whether it has been checked. more ›. "Our arithmetic" marks a figure this site computedLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more › from published numbers; "forecast" marks an official projection, not an outturn.
Twenty-one data centres in Scotland's council planning portals, and two more on the way. Around seven thousand three hundred megawatts. That's one campaign group's count. Here's what numbers that size mean, and who would pay.
On screen: Action to Protect Rural Scotland (campaign group), table updated 13 Aug 2026
Counts differ. Stop Climate Chaos Scotland, campaigners, in August: four thousand seven hundred to five thousand two hundred megawatts. A trade news site, in September: twenty-four proposals, up to six thousand, and that's a floor. Action to Protect Rural Scotland: around seven thousand three hundred, with estimates for some sites. Add schemes only in the grid queue: eleven thousand seven hundred and twenty. So: twenty-one to twenty-four sites, four point seven to seven point three gigawatts, depending on who counts.
On screen: Per row: Stop Climate Chaos Scotland (campaign group), Aug 2026 / resultsense.com (trade press), 8 Sep 2026 / Action to Protect Rural Scotland (campaign group), table updated 13 Aug 2026
The biggest scheme, Chapelcross in Dumfries and Galloway, is one thousand megawatts. Auchtertool in Fife, six hundred. Blackdog in Aberdeen is described as multi-gigawatt, starting at six hundred. Ten of the twenty-one listed sites come from one developer, Apatura.
On screen: Action to Protect Rural Scotland (campaign group), table updated 13 Aug 2026 (our count from the table) / resultsense.com (trade press), 8 Sep 2026
How big is that? Shetland HVDCHigh Voltage Direct Current: the technology used for long subsea electricity cables, including the Shetland link. more › Link 2 is one thousand eight hundred megawatts. Our arithmetic: seven thousand three hundred and six over eighteen hundred is about four of those cables. Even the lowest count is two point six.
On screen: OfgemThe UK government regulator for gas and electricity, which sets how much network companies can charge billpayers. more › / SSEN documents, 2024 / APRS / SCCS / Our arithmetic
Run seven thousand three hundred and six megawatts flat out for a whole year, eight thousand seven hundred and sixty hours, and our arithmetic gives sixty-four terawatt-hours. That's a ceiling: real load factors are lower, and no site publishes one.
On screen: APRS, table updated 13 Aug 2026 / Our arithmetic
Stop Climate Chaos Scotland says even its lower figure is more than Scotland's entire peak winter demand. Another campaign group puts that peak at just over four thousand megawatts, citing NESOThe National Energy System Operator, the body that keeps Great Britain's electricity grid balanced minute by minute. more ›. Another study says about six thousand. The comparison is theirs: true on their figure, contested on others.
On screen: Stop Climate Chaos Scotland (campaign group), Aug 2026 (peak figure as stated by SCCS, citing NESO) / ClimateXchange study, as cited (not opened by us)
Now the official case for. In May, NESO, the system operator, said growing demand in Scotland could help lower long-term bills across Great Britain. Five gigawatts of flexible demand behind Scotland's transmission bottlenecks, it said, could save consumers up to five billion pounds. A serious claim. So it gets the same test.
On screen: NESO press release, 13 May 2026
Those bottlenecks already cost money. NESO puts balancing and network-restriction costs for twenty twenty-five to twenty-six at three point one billion pounds. But the saving rests on one word. Flexible: demand that rises when wind is curtailedMoney paid to a generator to switch off, or reduce output, because the grid cannot carry all the power it is producing. more ›, and falls when it's short. Data centres, campaigners say, run twenty-four seven. No document we hold says these would flex. Five gigawatts of flexible demand is not the same thing as four point seven to seven point three gigawatts whose flexibility nobody has stated.
On screen: NESO press release, 13 May 2026 / SCCS, Aug 2026 / Our arithmetic
So who pays? In northern Scotland, the locational transmission demand charge was nil in twenty twenty-five to twenty-six. Grid upgrades to twenty thirty-one: about seventy billion pounds, recovered from bills. How much these sites would add, no document we hold says. In August, the UK state's National Wealth FundA UK government-owned investment body that can guarantee loans to infrastructure projects, backed by taxpayers. more › guaranteed two hundred and two million pounds of debt for two data centres in North Lanarkshire. A guarantee, not a payment, unless it's called. And the coast where Shetland HVDC Link 2 lands? Nothing from the community benefitMoney a developer or network owner pays to communities near new infrastructure, recovered in full from billpayers. more › guidance. Buried cable is excluded.
On screen: Per line: NESO Final TNUoSTransmission Network Use of System charges: the part of a bill that pays for building and running the high-voltage grid. more › Tariffs 2025/26, Table 9 / Ofgem estimateLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more › reported by the NAO, 2023-24 prices / Moray Firth Energy evidence registerA table listing every figure used on these pages, with its source document, its class and whether it has been checked. more › · Not established / National Wealth Fund, 18 Aug 2026 / Community benefit guidance, per evidence register
Since September, applications over fifty megawatts need an environmental impact assessment. Still unpublished: each site's load factor, flexibility and backup fuel. Until they are, the five-billion-pound saving is a forecast with a condition attached. The guarantee has already been given. Paid for by the public: as electricity billpayersAnyone who pays an electricity bill. Most of the costs on this site are recovered this way, not from taxes. more ›, and as taxpayers standing behind the loans.
On screen: Scottish Government Direction, 16 Sep 2026, as reportedA number taken directly from a company's own accounts or a regulator's own published document, not calculated or estimated by this site. more › by APRS / evidence register · Not established / NESO, 13 May 2026 / National Wealth Fund, 18 Aug 2026