The words are the author's; in the film an AI voice reads them. Register IDs link to the row of the evidence register that holds the document and line behind each figure. "Our arithmetic" marks a figure this site computedLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more › from published numbers; "forecast" marks an official projection, not an outturn.
Two power stations in Scotland do more than make electricity. Torness: nuclear, twelve hundred megawatts. Peterhead: gas, eleven hundred and eighty. Both spin heavy machines in step with the grid. EDF estimates Torness will stop in March twenty thirty. Peterhead has no published closure date. When they go, who keeps the grid steady?
On screen: DESNZThe UK government department responsible for energy policy, including subsidy auctions and community fund guidance. more ›, DUKES 2026 Table 5.11, 2026 · N20 / EDF station page and fleet update (press), 21 Jan 2026 · N45 / SSE plc Annual Report 2026 (filed), 2026 · K126
Three things. Inertia: spinning mass that resists a sudden fall in frequency. NESOThe National Energy System Operator, the body that keeps Great Britain's electricity grid balanced minute by minute. more ›, the system operator, says wind and solar don't synchronise in a way that provides it. System strength: current during a fault, which holds the voltage up. NESO says big coal and gas plants give five times the fault current of wind and solar. And black start: restarting after a total blackout. All of this came as a by-product of big spinning plant.
On screen: NESO explainer, 4 Dec 2020 · N116, N118 / National Grid ESO siting note for DESNZ, 2023 · N80, N119 / National Grid black start guide, v1.0, undated · N121
The dates, in the owners' own words. Torness was originally due to stop in twenty twenty-three. March twenty thirty is an estimateLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more ›, kept under review, subject to plant inspections. Peterhead holds a capacity contract to September twenty twenty-nine. Its proposed carbon-capture replacement has awaited consent since February twenty twenty-two, with no funding decision. Hunterston B, Scotland's other nuclear station, stopped in January twenty twenty-two.
On screen: EDF releases and station page (press), 7 Jan 2022 and 21 Jan 2026 · N45 / SSE plc Annual Report 2026 (filed) · K126, O103 / Scottish Government Energy Consents Unit, status checked 5 Oct 2026 · O101, O102
Critics say the closures are dates and the replacements are promises. NESO itself writes the strongest version. In twenty twenty-two: the imminent closure of nuclear stations in Scotland will lead to a loss of inertia. In March: inertia shortfalls could exceed twenty gigavolt-ampere seconds by the late twenty-twenties. Gas units kept for restarts may not stay warm. Miss the enablers: higher costs, and a missed clean power target.
On screen: NESO (then National Grid ESO) release, 6 Apr 2022 · N78 / NESO Operability Strategy Report, Mar 2026
The official answer: the spinning, without the burning. In twenty twenty-two NESO awarded ten contracts worth three hundred and twenty-three million pounds. Five synchronous condensers: motors that spin but generate nothing. Five grid-forming batteries, which mimic a generator. Ten-year contracts, from April twenty twenty-four. NESO estimates savings of about five hundred million pounds: a forecast. A tender for stability from twenty twenty-nine is not yet awarded.
On screen: NESO (then National Grid ESO) release, 6 Apr 2022 · N77 / NESO release, 11 Mar 2025 / NESO Long-term 2029 tender page, as saved 4 Oct 2026
Test it against the start dates bidders gave NESO. Rothienorman, a condenser: due May twenty twenty-four, running January twenty twenty-five. Blackhillock, the first grid-forming battery: due March twenty twenty-four, live March twenty twenty-five. Others ran up to twenty months late. At least six of the ten now run. Eccles, with almost forty percent of the inertia, was due this April; it's now expected in early twenty twenty-seven. In fairness, all would still run before Torness's estimated end.
On screen: NESO Stability Pathfinder Phase 2 tender results, 6 Apr 2022 / Quinbrook and Zenobē releases (company); NESO release, Jan 2025 – Apr 2026 / Our arithmetic · Register rows: N45
Or need less. NESO keeps a minimum of inertia. In twenty twenty-four that floor fell from one hundred and forty to one hundred and twenty. Next: one hundred and two, saving up to ninety-six million pounds a year. Consultees worried about the speed. OfgemThe UK government regulator for gas and electricity, which sets how much network companies can charge billpayers. more › did not approve it in December and asked for more evidence, then approved it in May, in stages. NESO points to twenty twenty-five, when three units tripped at once, and the system managed.
On screen: NESO Annual Balancing CostsWhat the system operator spends keeping electricity supply and demand matched second by second, including constraint payments. more › Report, Jun 2025 / Ofgem FRCR 2025 decisions, 12 Dec 2025 and 28 May 2026 · N83 / NESO FRCR, May 2025 · N82 / NESO Operability Strategy Report, Mar 2026
What isn't published? How much inertia Torness and Peterhead supply: we found no figure. Who holds black-start contracts in Scotland: a northern tender of fifty-three point eight million pounds names no providers. Which new units are live: no single NESO list. And by the end of this year, NESO must be able to restore sixty percent of demand within twenty-four hours of a total blackout.
On screen: National Grid ESO siting note, 2023 · N80 / NESO (then National Grid ESO) release, 4 May 2021 · N120 / NESO Operability Strategy Report, Mar 2026
So: the replacements are real, mostly built, and late. NESO's twenty twenty-five zero-carbon goal reached ninety-seven point seven percent, briefly. Torness's date is an estimate; Peterhead has none. Balancing costs are recovered through electricity bills. Paid for by the public: as electricity billpayersAnyone who pays an electricity bill. Most of the costs on this site are recovered this way, not from taxes. more ›, and as taxpayers standing behind the loans.
On screen: NESO Operability Strategy Report, Mar 2026 / NESO Annual Balancing Costs Report, Jun 2025 / NESO BSUoS charges page, as saved 4 Oct 2026
The film ends with a card carrying this site's address, its disclaimer and the address for corrections. If a figure is wrong, the correction route is on the About page.