The narration of film 4, scene by scene, as voiced, with the sources shown on screen in each scene. 5:01 · Watch or download on the Internet Archive · All eight films · Related page: The real cost
The words are the author's; in the film an AI voice reads them. Register IDs link to the row of the evidence register that holds the document and line behind each figure. "Our arithmetic" marks a figure this site computedLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more › from published numbers; "forecast" marks an official projection, not an outturn.
The government's own table puts offshore wind at one hundred and three pounds a megawatt-hour, for twenty thirty. Read the notes: for offshore wind alone, that leaves out the grid connection, and wider system costs are out of scope. So what does wind cost, counting the system around it?
On screen: DESNZThe UK government department responsible for energy policy, including subsidy auctions and community fund guidance. more ›, Electricity Generation Costs 2025 and Annex A · N95, O93, O100, N100
Start with the bottleneck. When the lines can't carry Scotland's wind south, generators are paid to turn down on one side, and up on the other. Across Britain: one point nine billion pounds last financial year, about nine point one billion over eight years. Most goes to gas stations turning up. Keeping Scotland's grid stable: ten-year contracts worth three hundred and twenty-three million pounds, at twenty twenty-one prices.
On screen: NAO HC 589 · K11, K13, K63; DESNZ RNP 2026 · K63; NESOThe National Energy System Operator, the body that keeps Great Britain's electricity grid balanced minute by minute. more › 6 Apr 2022 · N77, N78 · Register rows: K6
Scotland's share: about fifteen point six to sixteen point five billion pounds of subsidy so far, on this site's estimateLabels on the evidence register showing how strong a figure's source is: an official document, a press report, arithmetic, or an estimate. more ›. Now, about two billion a year, including switch-off payments. The Audit Office's counterpoint: most switch-off payments to wind stand in for subsidy the farms would have earned anyway.
On screen: This site's estimate · K5, K17, K19; NAO · para 1.11 in K17; DESNZ regional statistics · K21
Why so big? In twenty ten, connect and manage let generators join before the grid was ready. Forecast extra cost: about eighteen million pounds a year. By twenty fifteen, the rule's cost: one hundred and twenty-two million a year, with nearly zero forecast for twenty seventeen. Total constraint costsMoney paid to a generator to switch off, or reduce output, because the grid cannot carry all the power it is producing. more › now: one point nine billion. Not like for like. But plain.
On screen: DECC IA 27 Jul 2010 · K37, K42; OfgemThe UK government regulator for gas and electricity, which sets how much network companies can charge billpayers. more › monitoring reports · K40, K43; NAO · K11, K36, K47
Carbon. Contracts for DifferenceA government contract that tops up a wind farm's income when the market price is low, and claws money back when it is high. more › have paid thirteen point eight billion pounds for thirty-one point two million tonnes avoided. Our arithmetic: four hundred and forty-two pounds a tonne; offshore wind, five hundred and forty-five. The government values a tonne at two hundred and sixty. Caveat: the operatorThe company that owns or charters out a ship, as distinct from the client paying to use it for a particular job. more ›'s emissions factor has fallen by over two-thirds. At the early rate, it's about one hundred and eighty: below that value.
On screen: LCCCThe government-owned company that manages and pays out Contracts for Difference, and publishes the daily figures. more › actual CfD data · B42, B44, B45; DESNZ carbon values · B43; our arithmetic
Nuclear, on the same terms. Hinkley Point C: thirty-five to thirty-six billion pounds, in twenty fifteen prices. The Audit Office's earliest figure, same prices: seventeen point nine billion. About double. First power: five or six years late. Sizewell C: thirty-eight point two billion, which the Audit Office says is twenty-two per cent lower than the lowest current estimate for Hinkley Point C.
On screen: NAO Sizewell C · N8, N10, N133, N134, O139; NAO HPC 2017 · N9, N127; our arithmetic
Per megawatt-hour, Scotland's latest offshore wind auction: about eighty-nine pounds. Hinkley: one hundred and twenty-nine. Sizewell: an equivalent of one hundred and thirty-one to one hundred and fifty-five. The government's case for nuclear is our opening point, reversed: those prices leave out the costs of intermittent power. The Audit Office: benefits overtake costs only in twenty sixty-four, at the earliest. Scottish offshore wind's load factor last year: twenty-three point five per cent.
On screen: DESNZ AR7 · N36; NAO Sizewell C · N37, N39, N101; DESNZ regional, DUKES, VfM · N21, N22, N29, N32
The other options. North Sea oil and gas: the UK and Norway peaked at almost the same size. In twenty twenty-five the UK produced about a quarter of Norway's output. Both tax at seventy-eight per cent at the marginA profit figure expressed as a percentage of revenue, showing how much of each pound of income is kept as profit. more ›, built differently. The government calls the UK's fall natural decline. No regulator splits geology from policy.
On screen: NSTA · O5, O6, O7, O17; Sodir · O5, O6, O7, O19, O20; DESNZ · O33; O32 · Register rows: O12
Carbon capture: twenty-one point seven billion pounds over twenty-five years for two English clusters, at a cost close to offshore wind's. The Audit Office said the twenty thirty ambitions would be a struggle. Shale: officially, recoverable gas cannot be reliably estimated, and the only official yield figures equal two to four years of UK gas output. Fracking remains paused.
On screen: DESNZ · O91, O92, O93, O100; NAO · O107; BGS/DECC · O122–O124; DESNZ · O48; O131–O134; O125 · Register rows: O123
The UK's share of world emissions: about nought point six five per cent, or nought point six nine on the EU's measure. Of all fossil carbon dioxide since seventeen fifty: about four point three per cent. Weigh both.
On screen: DESNZ · K77; UNEP · K78; EDGAR · K79; OWID · K80; our arithmetic
Every option has a headline, a forecast and an outturn. Compare them on the same terms. Paid for by the public: as electricity billpayersAnyone who pays an electricity bill. Most of the costs on this site are recovered this way, not from taxes. more ›, and as taxpayers standing behind the loans.
On screen: DESNZ · O100; DECC IA · K42; NAO · N8, N134 · Register rows: K2
The film ends with a card carrying this site's address, its disclaimer and the address for corrections. If a figure is wrong, the correction route is on the About page.